An Bord Pleanala Permission for Wind Farm in Cork Quashed
In a recent court judgment at the end of 2014, O’Griana v An Bord Pleanala, Cork Co Council and Framore Limited, Justice Peart ruled that planning permission should not be granted for an windfarm project requiring a grid connection unless the grid connection details are provided in the Environmental Impact Assessment (EIA) process.
The case related to a 6 turbine wind farm in at Réidh na nDoirí, Ballingeary, Co. Cork and is one of many wind farm permissions which are currently being challenged in the courts.
To date planning authorities have accepted developers’ claims that details from ESB Networks are often not available at the time of planning and this element can be dealt with via a separate application subsequent to the application for the wind farm itself.
Essentially Justice Peart quashed the decision of An Board Pleanala to grant permission on the basis of ‘project splitting’, which is a recognised term for dividing up the true extent of a development. The grid connection for the proposed wind farm was considered to be an integral part of the project and the wind farm could not be dealt with as a stand-alone project in respect of EIA.
This decision could yet be appealed.
Published on January 5, 2015 By:David Mulcahy · Filed under: Court Cases, Green Energy; Tagged as: Cork, quash, wind farm