  • An Bord Pleanala have overturned the decision of Clare County Council to refuse a 10 year permission for a 5 turbine windfarm at Moneypoint Generating Station on the north shore of the Shannon Estuary. Each wind turbine will have an overall maximum dimension of 152 metres, comprising a tower 95-100 metres high, with a diameter of about four metres at the base, to which three blades of 52-55 metres length will be attached.

    The Council had refused permission based on the inadequacy of the Natura Impact Statement submitted by the applicant (ESB Wind Developments Ltd).

    The Board took the NIS submitted with the appeal into consideration along with their own Appropriate Assessment screening and determined that the proposed development, on its own or in combination with other plans or projects, would not adversely affect the integrity of a European site in view of the site’s conservation objectives. Presentation1

    The Inspector had recommended the omission of one turbine but, after studying the Environmental Impact Statement, additional information, technical reports including that of the Senior Executive Chemist together with submissions received from the applicant, the Board did not consider that there was a specific environmental risk arising from piling of ash as indicated for Turbine 1 given that this is inert and is located outside the engineered landfill area. Consequently, the risk of environmental pollution to the Special Area of Conservation would be negligible.

    Permission was granted subject to 14 conditions including a 25 year lifetime; cumulative shadow flicker arising from the proposed development, shall not exceed 30 minutes in any day or 30 hours in any year at any dwelling; fitting turbines with appropriate equipment and software to control shadow flicker at dwellings and a wind farm shadow flicker monitoring programme to be submitted to the planning authority for written agreement.

    Published on December 20, 2013 By:David Mulcahy · Filed under: Green Energy, Important An Bord Pleanala Decisions; Tagged as: , ,